ENVIRONMENT WAIKATO’S RULES
FOR
ON-SITE WASTEWATER DISCHARGES
![]()
File No:
56 80 12
Document No: 598657
Enquiries to:
Brent Fletcher
August 2002
Dear Sir/Madam
Some comments about the status Waikato Regional Council’s (Environment Waikato) permitted activity rules for onsite sewage treatment and disposal
Thank you for you inquiry about our rules for on-site sewage. Environment Waikato has permitted activity rules for the on-site treatment and disposal of domestic sewage. The rules have a number of criteria and if compliance with these criteria can be demonstrated then a resource consent (i.e. a specific discharge permit) is not required.
At present Environment Waikato has both a Transitional Regional Plan (July 1994) and an appeals version of the Proposed Regional Plan (February 2002). Both plans have rules about on-site sewage. The Regional Plan when fully operative will replace the Transitional Regional Plan.
The current status of the rules is that the Transitional Regional Plan is still relevant but so are the proposed rules. The appeals version of the Proposed Regional Plan is not yet fully operative because it has references (appeals) against it. It cannot be fully operative until the references have been decided in the Environment Court. At present it is partially operative.
In the meantime the way that the permitted activity rules for on-site sewage are applied is:
“The Transitional Regional Plan rules sets out the minimum requirements but we ask users to consider the direction set out in the appeals version of the Proposed Regional Plan. Rules or rule criteria that do not have references against them, are effectively available to be applied”.
We expect that the Proposed Regional Plan will become fully operative in about 12-24 months time.
For any inquiries about on-site sewage please phone 0800 800 402 in the first instance.
Yours faithfully
Brent Fletcher
Resource Officer,
Utilities Programme
Environment Waikato’s On-site
Sewage Rules as provided for in the (proposed) Regional Plan
The
Proposed Regional Plan is currently an appeals version of February 2002. This
means that the plan is now in a form that Council wants to adopt, and staff
will refer to the new plan for direction regarding resource use activities.
The
new rules for on-site sewerage are much the same as those that existed under
the Transitional Regional Plan.
The
table below sets out the reference numbers of the new rules as they will appear
in the Regional Plan as compared to the previous rules in the Transitional
Regional Plan:
|
Previous |
New |
|
Transitional
Regional Plan |
Regional
Plan |
|
Permitted Activity Rule 3.3.1 |
Permitted Activity Rule 3.5.7.5 |
|
Permitted Activity Rule 3.3.2 |
Permitted Activity Rule 3.5.7.4 |
|
Permitted Activity Rule 3.3.3 |
Permitted Activity Rule 3.5.7.6 |
|
Discretionary
Activity Rule 3.3.4 |
Discretionary Activity Rule 3.5.7.7 |
|
|
Prohibited Activity Rule
3.5.7.8 |
Should
you have any inquiries to make about the new rules, please contact the Waikato
Regional Council (Environment Waikato) on 0800 800 401 or 402.
The four on-site sewage rules of
the Transitional Regional Plan:
|
3.3.1 Permitted activity - discharge of domestic sewage from septic
tanks |
|
The discharge of domestic sewage
effluent (including grey and sullage water but not including stormwater)
into the ground from new on-site domestic sewage treatment and disposal
systems designed, constructed, operated and maintained in accordance
with New Zealand Standards Institute Standard Number 4610:1982 is a
permitted activity, provided that the following conditions are met: (a) The
volume of effluent to be discharged shall not exceed 1.26 cubic metres
per day averaged over any one month period. (b) The
discharge shall not cause or constitute a nuisance. (c) There
shall be no direct discharge of effluent into water. (d) The
minimum depth of unsaturated soil between the effluent disposal field
and the water table shall be sufficient to ensure bacterial reduction
so as to prevent adverse effects on the potability of any local ground
water supplies. (e) For
discharges from systems installed after 11 July 1994 the property area or the effective
disposal area for any one treatment and system discharge shall be no
less than 2500 square metres. |
The discharge
from a new septic tank is a permitted activity, subject to the following
conditions: - volume up to 1.26 m3/d - discharge shall not cause a nuisance - no direct discharge to water - minimum depth of unsaturated soil. - minimum area for new systems. |
|
Notes: • Septic tank design standard For the purposes of clarity, it is emphasised
that non-compliance with Standard 4610:1982 constitutes non-compliance
with this rule. • Ground water
supply Where ground water is used for potable
supply, due care needs to be taken in siting the sewage system. • Definition of “effective disposal area” For the purposes of this rule “effective
disposal area” is defined as that area of land that is available for
the infiltration and assimilation of effluent.
The “effective disposal area” may extend beyond property boundaries
provided an easement is registered on the title of the receiving property. |
Notes are provided on: - Septic tank design standard. - Ground water supply. - Definition of “effective disposal area”. - Discharge volume. - Nuisance. - Areas where rule does not apply. |
|
• Discharge volume A maximum discharge volume of 1.26 cubic
metres per day would allow for the discharge from a typically large
household. It would also cater for many small, intermittently used systems
for clubrooms, community halls, baches etc.
Water saving devices can be installed to control the volume to
be discharged. • Nuisance A “nuisnace” is any accumulation or deposit
(that) is in such a state or is so situated as to be offensive or likely
to be injurious to health. This
is not in substitution of the Health Act 1956. • Areas where rule does not apply |
|
|
In accordance with Council resolution concerning
the former General Authorisation for septic tanks, the following are
noted: - in
the case of Cooks Beach, this rule shall expire on 1 June 1995 - this rule shall not apply to the Allans subdivision north of Whangamata being described as Lots 1 to 7 DPS 32132 Block XII Tairua SD. |
|
|
3.3.2 Permitted activity - discharge of domestic sewage from existing
septic tanks. |
|
The discharge of domestic sewage effluent (include grey
and sullage water but not including stormwater) into the ground from
existing (installed before 11 July 1994) on-site domestic sewage treatment
and disposal systems maintained in accordance with New Zealand Standards
Institute Standard Number 4610: 1982 is a permitted activity provided
that the following conditions are met: (a) The volume of effluent discharged does not
exceed 1.26 cubic metres per day averaged over any one month. (b) The discharge shall not cause or constitute
a nuisance . (c) There shall
be no direct discharge of effluent into water. (d) The minimum depth of unsaturated soil between
the effluent disposal field and the water table shall be sufficient
to ensure bacterial reduction so as to prevent adverse effects on the
potability of any local ground water supplies. |
The discharge from an existing septic tank is a permitted
activity, subject to the following conditions: - volume up to 1.26 m3/d - discharge shall not cause a nuisance - no direct discharge to water - minimum depth of unsaturated soil |
|
Notes • Higher standard anticipated in future Septic tank systems provide a minimal degree
of effluent treatment. It is
anticipated that a higher standard of discharge than that provided by
septic tanks, will be required after the first review date of this plan. • Survey of ground water problems As part of the implementation of this rule
Environment Waikato will undertake a survey of potential problem areas
in conjunction with territorial local authorities, to determine where
local ground water problems occur.
Such a survey will be undertaken within five years of the operative
date of this plan and in accordance with policy 3.2.4. • Septic tank design standard For the purposes of clarity, it is emphasised
that non-compliance with Standard 4610:1982 constitutes non-compliance
with this rule. |
Notes are provided on: - Higher standard anticipated in future. - Survey of ground water problems. - Septic tank design standard. - Discharged volume. - Nuisance. - Areas where rule does not apply. |
|
• Discharge volume A maximum discharge volume of 1.26 cubic
metres per day would allow for the discharge from a typically large
household. It would also cater for many small, intermittently used systems
for clubrooms, community halls, bashes etc.
Water saving devices can be installed to control the volume to
be discharged. • Nuisance A “nuisance” is any accumulation or deposit
(that) is in such a state or is so situated as to be offensive or likely
to be injurious to health. This
is not in substitution of the Health Act 1956. • Areas where rule does not apply |
|
||
|
In accordance with Council resolution concerning
the former General Authorisation for septic tanks, the following are
noted: - in
the case of Cooks Beach, this rule shall expire on 1 June 1995 - this
rule shall not apply to the Allans subdivision north of Whangamata being
described as Lots 1 to 7 DPS 32132 Block XII Tairua SD. |
|
||
|
|
3.3.3 Permitted activity - discharge of domestic sewage from on-site
domestic sewage treatment and disposal systems. |
|
|
|
The discharge of domestic sewage
effluent (including grey and sullage water but not including storm water)
into the ground from on-site domestic sewage treatment and disposal
systems (excluding those designed and constructed in accordance with
New Zealand Standards Institute Standard Number 4610 : 1982) is a permitted
activity provided that the following conditions are met: (a) The
volume of effluent to be discharged shall not exceed 3 cubic metres
per day averaged over any one month period. (b) The
discharge shall not cause or constitute a nuisance. (c) The
design and construction of the system shall achieve the following criteria: - pre-treatment of effluent to a standard
unlikely to cause clogging of the disposal system or soils - isolation of the disposal field from
direct contact with ground water - no degradation of ground water quality
such that, as a result of the discharge, or in combination with other
discharges existing and reasonably foreseeable uses will be compromised - no degradation of surface water quality
as a result of the discharge, or in combination with other discharges - no direct discharge of effluent into
ground water or surface water. This
condition shall be satisfied by: - certification by a suitably qualified
and experienced practitioner that the system will consistently satisfy
the criteria, or - provision of appropriate documentation
which demonstrates achievement of the criteria. (d) The
system shall be managed and maintained in accordance with good practice
and in accordance with any requirements or recommendations specified
in any relevant code or guidelines related to the particular system. |
The discharge of domestic sewage from on-site domestic sewage treatment and disposal systems
is a permitted activity, subject to the following conditions: - volume up to 3 m3/d - avoidance of nuisances - design standards to be achieved - management and maintenance requirements. |
|
Notes: |
Notes are provided on: |
|
• Ground water supply Where ground water is used for potable
supply, due care needs to be taken in siting the sewage system. • Discharge volume A maximum discharge volume of 3 cubic metres
per day would provide for the equivalent of approximately 15 persons
average occupancy. This will cater for many small amenities
such as motels, clubrooms, etc. Water
saving devices can be installed to control the volume to be discharged. |
- siting - discharge volume - application of rule to communities - suitably qualified and experienced practitioner - appropriate documentation - nuisance. |
|
• Application of rule to communities For the avoidance of doubt, this regional
rule covers the situation where modern on-site sewage systems are proposed
for a community, or other group of properties. In this case, a community or group as a whole could obtain an
engineer’s certification, or provide information about its on-site sewage
discharges, to meet the conditions of the rule. This means that property owners would not need to individually
obtain engineering certification, or individually provide the required
information. · Suitably qualified and experienced
practitioner A “suitably qualified and experienced practitioner”
is a person who is qualified and experienced in the field of on-site
sewage treatment and disposal. · Appropriate documentation Documentation which demonstrates that the
on-site effluent disposal system installed achieves the criteria. Documentation may be in the form of a letter
or certificate outlining the specifications of a system and compliance
with the criteria. • Nuisance A “nuisance” is any accumulation or deposit
(that) is in such a state or is so situated as to be offensive or likely
to be injurious to health. This is not in substitution of the Health Act 1956. |
|
|
3.3.4 Discretionary activity - other on-site sewage discharges |
|
The discharge of on-site domestic
sewage effluent into the ground from a system or in a manner outside
the scope of or unable to meet the conditions pertaining to rules 3.3.1,
3.3.2 and 3.3.3 is a discretionary activity. |
Any discharge which is inconsistent with the “permitted
activity” rules is a discretionary activity. |
|
Note: |
|
|
• Consent conditions and notification Conditions for these consents, if granted,
will be determined on a case by case basis. Notification requirements will be determined
in accordance with s94 of the RMA. 3.4 ANTICIPATED
ENVIRONMENTAL RESULTS |
Consents for these activities will be determined on a
case by case basis. |
|
It is anticipated that the policies and rules for on-site
domestic sewage discharges will have the following environmental results: - ground water uncontaminated by sewage effluent
in new areas of on-site domestic sewage system use - avoidance of subsequent effects on surface
waters - reduced incidence of “public health” issues
associated with on-site sewage disposal - non-proliferation of septic tanks or systems
similar to the provisions of NZS:4610:1982 in intensively developed
areas - appropriate solutions developed in areas
where existing problems found to occur. |
Anticipated environmental results are as follows: - clean ground water - no effects on surface waters - fewer public health issues - septic tanks not in developed areas - solutions to problems. |
Rule 3.5.7.8 – Prohibited Activity – discharge of
untreated human effluent to water
|
The
discharge of domestic sewage effluent (including
grey water but not including stormwater) into land from an on-site domestic sewage treatment
and disposal system that was lawfully established or authorised before the
date of notification of this Plan (28 September 1998), is a permitted activity subject
to the following conditions:
a
The volume of effluent to be discharged from any one system
shall not exceed 1.3 cubic metres per day averaged over any one month period.
b
There shall be no direct discharge of effluent into water.
c
The
minimum depth of unsaturated soil between the effluent disposal field and
the water table shall be no less than 600 millimetres.
d
The discharge shall not result in any objectionable effects from odour beyond the boundary of
the subject property.
e
For discharges from systems installed after 11 July 1994, the
effective disposal area*
for any treatment and disposal system shall be no less than 2,500 square metres.
f
For discharge from properties which, at the date of authorisation
of the system, exceeded 2,500 square metres, this rule shall not apply where,
subsequently, the effective disposal area*
is reduced to less than 2,500 square metres.
g
For discharges from properties which, at the date of authorisation
of the system, were less than 2,500 square metres, this rule shall not apply
where, subsequently, the effective disposal area is reduced.
h
The discharge
shall not occur within 20 metres of a Significant Geothermal Feature.
i
From
1 January 1 2006 the septic tank shall be fitted with an effluent outlet filter.
j
There shall be
no adverse change in ground water quality as a result of the discharge, or
in combination with other discharges.
Advisory Notes:
·
The process for assessing
odour is specified under Section 6.4.1.3 of the Plan.
·
Discharges of contaminants into or onto land within
20 metres of a Significant Geothermal Feature are addressed by the Rules 7.2.6.1
and 7.2.6.2 of this Plan.
·
These existing systems
will generally be adequate provided that land and soil conditions are suitable
and that regular filter cleaning and desludging is undertaken.
·
Should
the treatment and/or disposal system fail to the extent that more than routine
maintenance such as desludging and filter cleaning is required to reinstate
the system, it will no longer comply with this rule and should be upgraded
to meet the conditions of Rule 3.5.7.5 or 3.5.7.6.
[NB – italicised
criteria are those subject to appeal]
Permitted Activity Rule 3.5.7.4 – existing
on site systems


![]()
·
Volume of discharge not more than 1.3 m3/d ·
Min. soakage field separation distance to g.w.t is 600mm ·
No direct discharge to water ·
Avoidance of nuisances ·
Systems installed after 11.7.94 section size (effective disposal area) to be at least
2500m2 ·
Should failure occur & more than routine maintenance is required to reinstate the
system, then upgrading will be required. ·
Effluent filter fitted to tank by 01.01.06

The
discharge of domestic sewage effluent (including
grey water but not stormwater) onto or into land from an
on-site domestic sewage treatment
and disposal system lawfully established or authorised after the date of notification
of this Plan (28 September 1998), is a permitted activity subject
to the following conditions :
a
The volume of effluent to be discharged from any one system
shall not exceed 1.3 cubic metres per day averaged over any one month period.
b
The minimum total septic tank size shall be no less than 3,000
litres.
c
There shall be no direct discharge of effluent into water.
d
There shall be
a zone of unsaturated soil of no less than 600 millimetres between the base
of the effluent soakage trench and the top of the water table at all times
of the year.
e
The discharge shall not result in any objectionable odour beyond
the boundary of the subject property.
f
The effective
disposal area* for any one treatment and disposal system discharge
shall be no less than 2,500 square metres. The discharge shall no longer comply
with this rule where the effective disposal area*
is subsequently reduced to less than 2,500 square metres.
g
The sewage disposal system shall not be sited within 30 metres
of a Natural State Water Body or Fisheries Class Water Body as
specified in the Water Management Class Maps and 10 metres from any other
surface water body.
h
The sewage disposal system shall not be sited within 30 metres
of a potable water supply well unless the well is drawing from a separate,
confined aquifer.
i
The discharge
shall not occur within 20 metres of a Significant Geothermal Feature.
j
The septic tank
shall be fitted with an effluent outlet filter.
k
There shall be
no adverse change in ground water quality as a result of the discharge, or
in combination with other discharges.
Advisory Notes:
·
The process for assessing
odour is specified under Section 6.4.1.3 of the Plan.
·
It is recommended that
on-site systems are designed, constructed, operated and maintained in accordance
with (Auckland Regional Council 1994 On-site Wastewater Disposal From Households
and Institutions – Technical Publication 58).
·
Discharges of contaminants into or onto land within
20 metres of a Significant Geothermal Feature are addressed by the Rules 7.2.5.12
and 7.2.5.13 of this Plan.
[NB – italicised
criteria are those subject to appeal]
Permitted Activity Rule 3.5.7.5 – new
on site systems


![]()
·
Volume of discharge not more than 1.3 m3/d ·
Min. tank capacity is 3,000 litres ·
Effluent filter on tank outlet ·
Min. soakage field separation distance to g.w.t is 600mm ·
No direct discharge to water ·
Avoidance of nuisances ·
Section size (effective disposal area) to be at least 2500m2 ·
Should failure occur & more than routine maintenance is required to reinstate the
system, then upgrading will be required.

Except
as provided for by Rule 3.5.7.5, the discharge of domestic sewage effluent (including
grey water but not including stormwater) onto or into land from an on-site domestic sewage treatment
and disposal system is a permitted
activity subject to the following conditions:
a
The volume of effluent to be discharged shall not exceed three
cubic metres per day averaged over any one month period.
b
The design, construction, operation and maintenance of the
system shall meet the following standards:
i.
pre-treatment of effluent to a standard not to exceed concentrations
of 20g/m3 of Biological Oxygen Demand and 30g/m3 of
suspended solids
ii.
there shall be
a zone of unsaturated soil as measured vertically between the bottom of the
soakage field discharge line and the top of the ground water table at
all times of the year, which shall be no less than 600 millimetres
for conventional trenches, beds and mounds, or 300 millimetres where dripper
irrigation lines are used and the design loading rate for effluent disposal
is less than five millimetres/day
iii.
there shall be no adverse change of ground water quality as
a result of the discharge, or in combination with other discharges
iv.
there shall be no adverse change of surface water quality as
a result of the discharge, or in combination with other discharges
v.
there shall be no direct discharge of effluent into ground
water or surface water.
c
The discharge shall not result in any objectionable effects from odour beyond the boundary of
the subject property.
d
The sewage disposal system shall not be sited within 30 metres
of a Natural State Water Body or Fisheries Class Water Body as
specified in the Water Management Class Maps and 10 metres from any other
surface water body.
e
Written proof of compliance with this rule shall be provided
to the Waikato Regional Council on request in the form of either:
i
certification by a person who is qualified and experienced
in the field of on-site sewage treatment and disposal that the system will
consistently satisfy the above standards taking into account the relevant
site constraints, or
ii
documentation which demonstrates achievement of the standards.
f
The discharge
shall not occur within 20 metres of a Significant Geothermal Feature.
[NB – italicised
criteria are those subject to appeal]
an advanced type
of
sewage treatment and disposal system
![]() |
![]() |
![]() |
·
volume of discharge not more than 3.0 m3/d
·
20:30 BOD/SS effluent quality requirement
·
avoidance of nuisances
·
no direct discharge to water
·
min soakage field separation distance to g.w.t is 600mm for
conventional soakage lines (e.g LPED) or 300mm when dripper line irrigation
is used.
·
design standards to be achieved
·
management and maintenance requirements
The discharge of domestic sewage effluent from on-site domestic sewage treatment and disposal systems onto or into land and any subsequent discharges of contaminants into air, in a manner which does not comply with Rules 3.5.7.4, 3.5.7.5 and 3.5.7.6 is a discretionary activity (requiring resource consent).
Exclusion to Rule 3.5.7.7:
Discharges of contaminants within 20 metres of Significant Geothermal
Features are excluded from this rule. The effects of these activities are managed by
Rules 7.2.6.1 and 7.2.6.2 of the Plan.
3.5.7.8 Prohibited
Activity Rule – Discharges of Untreated Human Effluent to Water
The discharge of untreated human effluent to water is a prohibited activity.
On site sewage - permitted activity compliance
What
type of information should be provided to demonstrate that compliance with
the permitted activity rule can be met?
The
information provided should include but not be limited to the following:
· a description of the site where the disposal will take place, which should include:
· the topography of the site (e.g. slope, prevailing wind direction, whether the site is in the sun part of or all day).
·
the depth of the spring ground water table level below the
ground surface.
· a site sketch or plan should be included with this information.
·
the size of the disposal field (m2) its proximity
to a) any open waterways, and b) to any bores within 500 metres of the disposal
field.
·
a description of the sewage treatment and disposal system,
and its operation.
·
a description of the soil types that are located within the
area of the property where the effluent is to be disposed of. This should
include a soil profile description from at least three points within the soakage
area proposed and also include the designed rate of effluent loading onto
the soil in mm/day.
·
cleaning and maintenance requirements.
·
In areas where there is a already a number of septic tank discharges,
any recent groundwater sampling results would be desirable particularly results that show
the levels of nitrate and faecal coliforms present in local groundwater (if
any). Of particular interest to Environment Waikato are areas where there
are free draining soils, poor draining soils and/or where there is a high
groundwater table.
It
is strongly recommend that if you are likely to have difficulty in providing
the type of information described above, that the assistance of an on-site
wastewater treatment and disposal expert be sought. (This should be someone
who is highly trained and informed in the principles, design and application
of on-site sewage systems).
To alleviate some of the confusion over what type of systems are acceptable under the criteria of the Regional on-site sewage rules 3.3.3/(3.5.7.6), the following explains:
The rules envisage an improved type of treatment and disposal system which is typically a large multi-chambered unit incorporating an effluent filter and some sort of extra treatment stage to ensure that a high standard of wastewater treatment is attained. This type of system is considerably more advanced than a basic septic tank and its associated effluent soakage trench. Rule 3.5.7.6 requires that the effluent produced from these types of systems is to be of a quality in terms 20 mg/L of Biological Oxygen Demand and 30 mg/L Suspended Solids (i.e. 20:30 BOD/SS). This is a secondary standard of treatment. Septic tanks with filters are unlikely to be able to meet this treatment standard as it generally requires some form of secondary biological treatment to achieve – for example by active aeration (aerated system) or passing through a packed bed reactor (sand filter or textile filter or similar).
On particularly restricted sites where very tight soils (poor draining) or very sandy soils (fast draining) predominate, a very high standard of effluent treatment may be required. For example the system may need to incorporate a re-circulating sand contactor, or provide extended effluent treatment such as an activated system (aeration). On difficult soils the effluent soakage field provided should be larger rather than smaller. The effluent loading rate of the soil should be low (typically less than 10mm/day).
In situations where there is a seasonal or permanently high
water table the effluent soakage field may also need to be mounded up in order
to provide an appropriate separation distance of unsaturated soil. This is
the distance required from the bottom of the soakage field distribution line
to the top of the groundwater table. It is necessary to ensure final renovation
of the effluent by the soil for protection of the groundwater table from harmful
contaminants and to promote some further breakdown of undesirable nutrients
that are contained in wastewater.
Generally effluent discharged from these types of systems should be pump dosed, although certain types of siphon dosing are also available.
Where doubt exists as to the applicability of a particular system, it is up to the applicant to provide information that demonstrates that the criteria of rule 3.3.3/(3.5.7.6) will be achieved by the system proposed. In many instances where compliance with rule 3.3.3/(3.5.7.6) is sought owners would be well advised to engage a wastewater treatment and disposal expert to carry out a full site evaluation and then to design an appropriate system for them.
Where upgrading of a basic single chambered septic tank system is being considered rather than total replacement, there are a number of options available, ranging from add on secondary chambers to the fitting of special filters (contactors) after the existing tank. Generally, if the septic tank was installed in line with the old New Zealand Standard NZS4610:1982 it will not be of sufficient treatment capacity compared to the types of systems envisaged in terms the criteria of the new rules.
Improved types of systems – examples
|
|
|
|||
|
|
|
|||
|
|
|
|||
|
|
|
|||
|
|
||||
Some other information about:
§
wastewater flow design
allowances
§
site soil types
§
soakage trench and soakage bed
loading rates,
§
Long Term Acceptance
Rates (LTAR)
i.e. how to work out how much soakage area is required
§
Some of the photocopied
information is from:
The
New Zealand Manual of Alternative Wastewater Treatment and Disposal Systems,
Volume II Part A
ON-SITE WASTEWATER
DISPOSAL FROM HOUSEHOULDS AND INSTITUTIONS, Auckland Regional Council, Technical Publication No. 58, November
1994 (written by Ian Gunn for ARC).⨪
Some comments about
soakage fields
It is important that
the soakage field is correctly set up. This can be done by considering the
volume of effluent that is to pass through the field in line with the characteristics
of the soil on/in which it is to be located.
Bernhart’s Design Principle is one method of working out the appropriate soakage field
size in line with the long term acceptance rate of the soil (LTAR).
Example:
A
= F x L
where
S A = bottom of bed/trench area (m2)
F = daily wastewater flow (litres)
S = the bed loading rate (mm/day)
L = pollution factor (NZ = 1.0)
Assume:
· 5 person household with normal fixtures @ 180 l/pp/day.
· Soil type category 3 – medium fine and loamy sand (good drainage).
· Trench loading rate from table 8.1 (TP58), LTAR is 20 – 30mm/day.
· No obvious restrictions on-site, (i.e. groundwater is deep, soils are consistent and bore or stream in close proximity of soakage area).
Calculation to determine length of trench required:
A
= F x L
where
S A = ? m2 (the unknown factor).
F = 5 x 180 = 900 litres.
S = 30 mm/day.
L = 1.0
A = 900 x 1
30
= 30 m2. The required trench area is 30m2.
If the trench width is to be 450mm, the length of trench required will be:
30 (m2)
0.45 (m1)
= 67 metres.
Similarly, if the trench width is to be 600mm, the length of trench required will be:
30 (m2)
0.60 (m1)
= 50 metres.
